By Zhou Mingli
This August marks the first anniversary of the smooth operation of Concourse H at Terminal 4 of King Khalid International Airport in Riyadh, Saudi Arabia.
At handover, the client, Riyadh Airports Company, praised the project in a letter of commendation: it was the company's first project in nearly 20 years to be completed on schedule.
With a floor area of approximately 19,500 square meters, this aviation facility stands in the heart of the desert, offering passengers more efficient, seamless connections and a comfortable place to wait for their flights. Over nearly two years, China Airport Construction Group (hereinafter "CACC") worked side by side with 35 professionals from Saudi Arabia, Egypt, Sudan, India and Pakistan. Together, they turned a design blueprint into a built reality amid the sands. The project is a vivid example of China's civil aviation sector contributing to international cooperation under the Belt and Road Initiative (BRI).
The project site lies next to the busy terminal and airfield areas, making construction in an operational airport environment particularly high-risk. The works covered architecture, structural engineering, fire protection, HVAC, water supply and drainage, aviation fuel, low-voltage systems, and aeronautical ground lighting. This called for rigorous safety controls and close coordination across disciplines and work sequences. As the main contractor, CACC assembled a joint team with its subsidiaries, including CACC Beijing International Engineering, Civil Aviation Airport Construction Engineering, and Civil Aviation Airport Chengdu Electronic Engineering Design.
The team brought to Saudi Arabia China's proven airport project management systems, experience in construction while airports remain operational, and integrated resource coordination.
Professionals from Saudi Arabia, Egypt, Sudan and other countries also joined the project. Drawing on their knowledge of local regulations, culture, market practices and Middle Eastern engineering standards, the team moved beyond a one-directional cooperation superficial "Chinese teams give instructions, international teams carry them out" approach. It established a working model in which Chinese and international team members assessed issues, discussed solutions and implemented them together, creating a deep localization to overseas project delivery.
Breaking Barriers: Bridging Cultural Differences
Building a Strong Partnership through Effective Collaboration
The first hurdle in an overseas project is often not technical; it is getting people to work well together.
Saudi Arabia has a mature construction market and a well-developed regulatory framework. The client set stringent requirements for construction quality, work standards and every detail of contract performance. Differences in thinking, communication and decision-making between the Chinese and international teams initially hindered technical coordination and progress on site.
Khalid, a Saudi employee, helped bridge that gap.
His role went far beyond interpreting. He was closely involved in procurement, supplier coordination and communication with the client. Having worked in the local construction market for years, he understood Saudi Arabia's building materials sector and business practices. He helped the Chinese team identify local material suppliers, understand production and delivery lead times, navigate approval procedures and follow commercial practices, closing gaps in its knowledge of the local market. He also explained the project's demanding technical specifications and quality standards to local suppliers, ensuring that material selection and production requirements met the design. Core suppliers were concentrated in a few locations, and approval and delivery procedures were rigorous. Verbal assurances alone could lead to deviations from specifications or schedule slippage, disrupting coordination among disciplines.
With Khalid's close support, the Chinese team adapted quickly to local requirements, refined its working practices and moved away from casual verbal communication. The project clearly documented key technical details, acceptance criteria, schedule milestones and commitments, then used standardized procedures and closed-loop management to uphold technical standards and schedule commitments.
"When the Chinese team says‘no problem', they follow it up with solutions and action". That was Khalid's assessment of the team. Through repeated exchanges on material checks, technical reviews with the client and on-site quality inspections, the Chinese team's practical, rigorous approach and follow-through helped remove obstacles to cooperation. The partnership evolved beyond simply passing information back and forth: the teams developed ways of working that suited both sides. This helped prevent technical discrepancies and gaps between work sequences at source, built trust for subsequent multidisciplinary coordination, strengthened the team's ability to collaborate effectively overseas, and laid a solid foundation for steady project progress.
Forging Ahead: Tackling Technical Challenges
Delivering Quality through Practical, Rigorous Standards
Late in the project, part of the south facade was redesigned to incorporate a glass curtain wall, creating a dual challenge for the schedule and the technical team. The time available for design development, procurement, logistics and on-site installation was extremely limited; a delay at any stage could affect overall handover.
Huda, an Egyptian architect, played a key role in this demanding effort. She had worked on an airport project in Kuwait and had years of experience in Middle Eastern infrastructure. Familiar with local airport construction requirements and approval procedures, she was responsible for architectural coordination and material selection on this project.
Throughout the facade variation, she took part in risk assessments, construction method reviews and schedule planning, and proposed several improvements based on site conditions. The Chinese facade and BIM teams worked in parallel on design development, required mock-up approval before full-scale installation, refined the detail junctions through repeated reviews, and translated the revised drawings into a workable construction plan suited to actual site conditions.
To keep the work on schedule, the project connected supply chains in China and Saudi Arabia and tracked progress throughout the process. Daily reporting and round-the-clock shifts helped maintain work on site. Technical discussions sometimes brought differing professional views, design approaches and construction methods into sharp relief. The team nevertheless applied one common standard: neither the merits of a technical solution nor the choice of construction method depended on anyone's nationality. The only test was whether it solved the practical problem, protected quality and maintained a safe schedule.
As the teams worked through these challenges, Huda grew from carrying out assigned tasks into a core member involved in technical assessments, solution development and risk management. Through the same collaboration, Chinese engineers learned how design approvals, material acceptance and local construction constraints worked in the Middle East, gaining valuable hands-on experience in high-end overseas civil aviation projects.
Tackling Critical Work: Getting the Hidden Works Right
Safeguarding Safety through Precise Coordination
Compared with visible facade work, concealed works such as underground utilities and above-ceiling MEP services involve complex sequences and less visible risks. They demand careful construction planning and coordination across disciplines, making them a key test of the teams’ technical capability and ability to work together. Yousef, a senior mechanical engineer from Sudan, coordinated MEP work, including fire protection and HVAC. He was familiar with the existing airport layout and local industry practices in Saudi Arabia. He anticipated construction risks and pointed out that records of utilities in the existing terminal were incomplete. Excavating without proper investigation could easily damage live services, causing rework and threatening airport operations. Meanwhile, MEP services had to be routed through limited spaces; if each discipline worked independently, clashes could obstruct subsequent work.
To manage the risks of concealed works, the project planned ahead and brought coordination forward. It established a joint Chinese and international working mechanism, with daily technical coordination meetings and regular joint site inspections. Using digital BIM tools such as Revit and Navisworks, the team ran clash simulations to identify potential issues early and adjust utility routes and work sequences. Chinese engineers, international technical specialists and site supervisors checked the drawings against actual site conditions together, resolving issues before construction and controlling the quality and safety of concealed works at source.
Yousef saw the value of this approach: "The daily coordination meetings and joint inspections are the most effective way to identify problems and improve communication". During work on high-risk systems such as aviation fuel pipelines and pressurized pipe networks, Chinese engineers responded quickly and acted decisively while maintaining strict safety controls. Yousef drew on his practical knowledge of local MEP systems to provide key technical support for risk identification and solution development. The Chinese team's ability to resolve issues quickly complemented local expertise. Together, the teams completed concealed works in underground and above-ceiling areas with precision, safeguarding the project's safety and quality.
Results: Bringing Diverse Strengths Together
Delivering Quality on Schedule to a High Standard
International projects are not simply a matter of bringing together people from different countries. They require the deep integration of diverse expertise, technologies and management systems, with decisions carried through to implementation. At Concourse H, the team gradually established a construction management system suited to local conditions and a collaborative approach designed for overseas projects. Site issues across nationalities and roles were addressed promptly, professional perspectives were incorporated into decisions, and the whole team was united in tackling challenges.
The project established a two-way coordination and control mechanism. Technical risks identified by international team members were quickly entered into a corrective-action process, while construction plans developed by the Chinese team were adapted to Saudi regulations and local supply chain conditions. This prevented gaps between technical plans and site realities and made implementation more effective. The Chinese team contributed overall planning, milestone control and implementation capacity; local professionals brought detailed knowledge of regulations, market practices and international standards. Their complementary strengths created an effective, mature model for international collaboration on overseas projects.
The project was completed successfully on June 30, 2025, and officially commenced trial operations on August 5. It recorded no major safety incidents or major quality issues, and the client highly commended the team's performance.
The smoothly operating concourse reflects the Chinese construction team's technical strength, disciplined approach to delivery and ability to overcome challenges. It also embodies the dedication and expertise of 35 international professionals. Bridging language and cultural differences, the teams worked together with care and commitment to deliver quality.
Cooperation under the BRI in civil aviation goes beyond completing projects and building facilities. It also enables technical exchange, mutual understanding between cultures and a two-way process of mutual engagement. The successful delivery of Concourse H at King Khalid International Airport demonstrates that Chinese civil aviation construction companies have not only strong technical capabilities, but also the ability to integrate across cultures, collaborate internationally and deliver high-quality projects. It is a vivid example of CACC's efforts to build a globally capable professional construction team.
In recent years, CACC has actively supported the BRI, deepened its presence in overseas infrastructure markets and steadily expanded its international business. From upgrading African aviation hubs and expanding and renovating airports in Central Asia to delivering high-standard terminals in the Middle East, CACC has continued to strengthen the international profile and competitiveness of China's civil aviation infrastructure through systematic project management and localized technical collaboration.
As the Silk Road enters a new chapter, China's airport construction sector is moving beyond one-way technology transfer and expansion overseas toward a new model of deeper engagement, local integration and shared benefits. It is entering a stage of high-quality development rooted in local markets, cultural understanding and mutual progress. Looking ahead, CACC will draw on its strong technical foundations and growing experience in overseas collaboration, guided by mutual trust in technology, cultural exchange and win-win cooperation. It will integrate more deeply into global infrastructure development, deliver high-quality projects tailored to local conditions, and continue to build the international reputation of China's airport construction sector along the routes that connect the world.